Confidential Warehouse
Rapid concrete and resinous floor takeoff for a Michigan contractor bidding a $1 million package in California — 2.3M SF RSP grinding, sealed concrete, polished concrete, and epoxy, turned over in eight hours.
- Location
- California
- Client
- Polished concrete & epoxy contractor
- Bid Value
- $1 million (1-day submit)
- Takeoff Time
- 8 hours
Fig. 01 — Project spotlight
What we took off.
Specialized heavy-duty concrete finishing and resinous flooring scopes quantified against architectural and structural specifications for a large-scale industrial facility.
- Robotic Platform Grinding (RSP)
- Polished Concrete
- Sealed Concrete
- Epoxy Flooring
- Electrical Scopes
What came back.
Precise square footage breakdowns by finishing specification, ready for immediate vendor pricing and qualified proposal submission.
- Microsoft Excel
- PDF Drawing Markups
Complete itemized sheets with transparent assumptions for design-phase bidding.
Eight hours to turn around a $1 million bid.
P2C completed the total takeoff in 8 hours, allowing the contractor to provide a comprehensive $1 million bid within a single day.
The project was bid during design when not all quantities were explicitly shown. Our estimators proactively communicated assumptions to the client so they could be cleanly qualified in the bid.
Fast Turnaround Time
P2C completed the total takeoff in just 8 hours, enabling the contractor to provide a $1 million bid within a single day.
Clear Communication
P2C estimators effectively communicated assumptions to the client, permitting them to be properly qualified in the bid.
Competitive Edge
Rapid, accurate bidding capability gave the contractor a significant competitive edge in securing the project.
Packages used on this bid.
Bidding a concrete or epoxy package this month?
Send the drawing set and your bid date. An estimator confirms scope before work starts and flags drawing conflicts rather than guessing past them.