P2C Construction Project-Site Improvements Project

Project Description

  • Location: Riverside, California
  • Client: Concrete Contractor Based in Southern California

P2C Takeoffs for

  • SOG
  • Footings
  • CMU Walls
  • Pavement
  • Sidewalk
  • Curbs
  • Rebar

P2C Takeoffs Details

  • Pavement: 31,000 SF
  • Slab on Grade:2,000 SF
  • CMU Walls: 290 SF

P2C Advantage

  • P2C completed the total takeoff in 8 hours and allowed the Contractor to provide a bid within 1 day.
  • The project takeoff was completed and communicated to the client utilizing their preferred method of Bluebeam Revu and MS Excel.

Key Benefits

  • Efficiency: P2C completed the entire takeoff process in just 8 hours, enabling the contractor to submit a bid within one day.
  • Accuracy and Precision: The takeoff covered various critical components like slab on grade, CMU walls, pavement, and rebar, ensuring a comprehensive and detailed analysis.
  • Client Centric Approach: The project takeoff was delivered using the client’s preferred tools, Bluebeam Revu and MS Excel, ensuring seamless communication and integration with the client’s systems.
  • Expertise in Key Areas: P2C’s experience with specific elements such as SOG, footings, and curbs enhances the reliability of the takeoffs, providing confidence to clients in the quality of the work.